@David Cutler I think the discussion is showing that there is a bit of a distinction between measuring internal or finishing items compared to civil works which is mainly due to the sizing of the products used.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
If I’m measuring groundworks then I certainly don’t make deductions for manhole covers, etc.. If you start going into that sort of detail then I think you’d also need to start adding in extra costs for working around the manholes, temporary protection, etc..
Things like drive areas and paving slab paths are all measured as per the drawings. The rates that we apply will allow for wastage. However, if someone designs a path at 1m wide using 0.60m wide paving slabs then we will increase the wastage factor significantly or possibly even measure the path as 1.20m wide.
Brickwork to houses is measured with the doors and windows deducted although I do know some people that still measure this gross. My argument with that is the percentage area of openings can vary greatly – maybe between 13 and 25%. The type of bricks or blocks is the thing that can have a significant impact on the wastage allowed. Some cut very easily whereas other (e.g. concrete bricks) have a tendency to shatter when they are cut.
Measuring roofing members is very different though. I will measure each individual rafter to the correct length then apply an allowance for cuts. The result is then rounded up to the nearest 300mm as this is the stage in which the standard lengths increase.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
@David Cutler can you create your own custom column with the appropriate status options? Leaving a blank (or single space) option in there?
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
I have a cheap Bluetooth mouse for when I go out on site.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
I ended up going for the Logitech G604 mouse. I’m making use of a lot of the keys but not all of them yet! 😅
As for the keyboard, my old one is still okay so I can wait to sort that out.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
@Doug McLean I can understand why you would do that with what you are measuring. Unfortunately, when I measure brickwork to houses not only can the % of openings vary massively but there are a load of other features that I probably need to pick up too.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
@David Cutler 🤣
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
Sorry – have just realised that you guys are probably thinking “lintel, cavity closer, etc – what is he talking about?!”. They are some of the joys of building in brickwork instead of timber frames.
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
I think I’ve worked out a way not only to deduct the door but to also add the lintel, cavity closer, etc all at with the same markup!
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
Tell them to markup the door first and then draw the wall around it – that way they won’t have to remove the door at all. 😁
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
Suggestion to Bluebeam for those? 😅
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
There’s a floor to @David Cutler .
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
@David Cutler I’m supposed to be having a look at a setup for someone soon!
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
So, do you save all of you documents to projects? If so, and you don’t use sets, how do you go about adding revised drawings, etc.?
-
Points: 13,517Rank: UC2 Brainery Blue Belt III
I did start out with an old formula which used Index and was rather ‘epic’ so was quite pleased to find the new formulas.
The problem that I found with the Bookmarks pdf is that it is just one continuous list and therefore several pages long.
As for Sets, I would love to be able to use these, but I won’t go into that as I think everyone has heard me moaning enough about those not working for me! ☹