    I hear this one a lot, and I think it’s one of the most relatable frustrations in wall and finish takeoffs. You measure the elevation, you feel good, and then a little voice in the back of your head asks, “Did I take out every opening?” With three windows, it’s easy. With sixty across four elevations, you start wondering if the number on your screen is a number or a hope.

    So I’m curious how you handle deductions:

    • Cut them out of the area as you go

    • Measure the openings separately and subtract at the end in Excel

    • Just consider it waste and move on.

    • Something else entirely (I’d love to hear it)

    And the one I really want to hear about: what’s your last check before that number goes into the bid?

    No
    wrong answers. If you’re newer to takeoffs, this is a great place to ask your
    own questions too. Come learn alongside the rest of us.

    Doug McLean replied 2 weeks, 4 days ago 4 Members · 10 Replies
  • 10 Replies
  • Vince

    Member
    October 19, 2026 at 10:08 am
    Points: 17,066
    Rank: UC2 Brainery Advanced Blue Belt II UC2 Brainery Advanced Blue Belt II

    I’ll measure the elevations to a building and then do cut outs for the window & door openings.
    I then use new markup tools to fill in the cut outs. The area of a window or door obviously isn’t of much use if you’re a bricklayer, cladder, etc. but you can then use these markups to automatically generate information such as the number of formers, lintel details, dpc trays, cavity closers to reveals, etc..

    • Troy DeGroot

      Organizer
      October 20, 2026 at 12:18 pm
      Points: 30,641
      Rank: UC2 Brainery Advanced Brown Belt II UC2 Brainery Advanced Brown Belt II

      Good use for those cutout measurements. Do you hold the Shift Key to fill them all with one click?

      • Vince

        Member
        October 21, 2026 at 5:00 am
        Points: 17,066
        Rank: UC2 Brainery Advanced Blue Belt II UC2 Brainery Advanced Blue Belt II

        I fill them individually with a click each time as I fill different openings with different markup tools.
        There are different options of door openings as some may have returned internal reveals, some may need dummy frames whilst other use formers, etc..
        Then the windows are allocated to ground floor, first floor, eaves level, etc. as they may have different types of lintel, bed reinforcement above & below the openings, etc, etc, etc…

        • David Cutler

          Member
          October 21, 2026 at 7:26 am
          Points: 35,150
          Rank: UC2 Brainery Red Belt UC2 Brainery Red Belt Rank

          Sounds as if the only thing that is consistent is the inconsistency @Vince ! 😎

        • Troy DeGroot

          Organizer
          October 21, 2026 at 2:32 pm
          Points: 30,641
          Rank: UC2 Brainery Advanced Brown Belt II UC2 Brainery Advanced Brown Belt II

          Always fun juggling the smallest of variables.

  • Doug McLean

    Member
    October 22, 2026 at 2:53 pm
    Points: 19,387
    Rank: UC2 Brainery Advanced Blue Belt IIII UC2 Brainery Advanced Blue Belt IIII

    Short answer, I ignore them.

    Long answer, it depends.

    If the opening is significant, then I just won’t even mark them up, but even that depends.

    In Millwork, in something like Wall paneling, depending on how the grain sequencing and matching is specified, I may have to take off the full panel regardless. In those cases the customer is PAYING for the waste to meet the spec.
    For example, if we get a spec where the veneer has to be sequence matched and there is a window in the elevation with paneling on all four sides of the window, I need to allow for all that veneer in the middle so that we can maintain the sequence.

    • David Cutler

      Member
      October 23, 2026 at 7:13 am
      Points: 35,150
      Rank: UC2 Brainery Red Belt UC2 Brainery Red Belt Rank

      Makes perfect sense @Doug McLean

      So, do you folks have piles of window cutout scrap all over the place? As a Dad I can never get rid of a cutoff as I’m sure I will find a use for it some day! 😎

      If you have trim around said window I’d assume that you take that off independently.

      • Doug McLean

        Member
        October 23, 2026 at 9:16 am
        Points: 19,387
        Rank: UC2 Brainery Advanced Blue Belt IIII UC2 Brainery Advanced Blue Belt IIII

        we try not to let it pile up… lol

        • Troy DeGroot

          Organizer
          October 27, 2026 at 10:42 am
          Points: 30,641
          Rank: UC2 Brainery Advanced Brown Belt II UC2 Brainery Advanced Brown Belt II

          I briefly worked at a woodshop and regularly found some pretty cool scraps in the dumpster. Yeah, I said it. 🤣

          • Doug McLean

            Member
            October 28, 2026 at 3:36 pm
            Points: 19,387
            Rank: UC2 Brainery Advanced Blue Belt IIII UC2 Brainery Advanced Blue Belt IIII

            you should see the pile of Acacia 12/4 live edge slabs we have left over from a project